The west end of 12th Avenue South will stay fenced through the winter, and for the first time since Hurricane Ian no part of the Naples Pier is open. That shifts the Olde Naples beach day a little to each side. The two beach ends next to the pier, Broad Avenue South and 13th Avenue South, now handle the walk-ups, restroom stops and sunset crowds that used to end at the pier. In mid-November the Third Street South Farmers Market moves back onto the same two-block span between Broad and 13th. Until July 2027, those two avenues are the closest thing the neighborhood has to a front door.
The 100 feet that stayed open, and when they closed
After Ian came through on September 28, 2022, about 100 feet of the pier was still standing, and that section reopened in November 2022, according to Naples Press. That short stub got the neighborhood through three winters. Then the City held a groundbreaking on January 5, 2026, construction started the next day, and demolition of the old pier was finished by April 13.
Last season had the pier until January. This season has none of it, from first cold front to Easter. The City of Naples project page lists what is closed for the project's run of roughly 18 months:
- The pier, its stairs, restrooms and showers
- 12th Avenue South west of Gulf Shore Boulevard South
- The eastern two-thirds of the pier parking lot at 12th Avenue South and Gulf Shore Boulevard South, while the western third stays open for limited public parking
The landmark at the end of the street has been rebuilt again and again since 1888. Before this project it drew more than a million visitors a year. With the pier closed, beach access near 12th Avenue South now goes through the two neighboring beach ends.
Broad and 13th, the two doors the City kept open
The City set up pedestrian bypasses at the Broad Avenue South and 13th Avenue South beach ends. Both stay open for the whole project, and both have restrooms. That restroom detail matters more than it sounds. In March, the Naples Daily News reported that portable toilets at the site had upset some beachgoers, and that officials were working on the sanitation complaints and looking for a longer-term fix during construction.
The fence hasn't kept people from watching. WINK News reported visitors stopping to watch the work while the pier was closed. Local residents it spoke with welcomed the progress, and one visitor said he missed fishing there. From either bypass, the build is close enough to follow week to week.
The farmers market lands on the same two blocks in November
The Third Street South Farmers Market runs every Saturday of the year, 7:30 to 11:30 a.m. From May through November it sits in the Neapolitan parking lot between Third Street South and Gordon Drive. From mid-November through April it moves onto Third Street South itself, between Broad Avenue South and 13th Avenue South. The Paradise Coast listing shows Saturday dates on October 24, October 31, November 7 and November 14. It doesn't give the exact Saturday for the 2026 move.
So once the market is back on the street, a Saturday morning in Olde Naples starts and ends on the same pair of avenues. Produce, flowers, pastries and coffee are on Third Street between Broad and 13th. A few blocks west on those same two avenues are the only open beach access points near the pier. The holiday calendar lands in the same spot:
| Date | Event | Where |
|---|---|---|
| October 31, 3 to 5 p.m. | Halloween Spooktacular, followed by Evening on Fifth from 5 to 8 p.m. | Cambier Park and Fifth Avenue South |
| November 14, 10 a.m. to 4 p.m. | Fine Arts & Craft Show | Cambier Park |
| Monday, November 23, 6 to 9 p.m. | Naples Tree Lighting | Third Street South |
| Thanksgiving week, Tuesday through Saturday | North Pole on Third, with live music 5 to 8 p.m., snowfall at 7 p.m., shops open until 7 p.m., and nothing on Thanksgiving Day | Third Street South |
| November 28, 10 a.m. to 4 p.m. | Art in the Park | Cambier Park |
| December 4 and 5 | Christmas Walk and Tree Lighting | Fifth Avenue South |
| Saturday, December 12, 1 to 3 p.m. | Santa Paws | Third Street South |
The dates come from the Third Street South holiday page and the Fifth Avenue South events calendar. Both organizers can change them, so check close to the day.
What goes up offshore between now and July
Most of the hard work is already underwater. On October 7, Shoreline Foundation Inc. drove the last of the 193 reinforced-concrete pilings the new pier needs. The City's timeline shows the rest of the order:
- June 26, 2026. The first concrete pour for the bents, the rows of pilings capped by a crossbeam. The full project needs about 602 cubic yards of concrete.
- September 18, 2026. The concrete pour for the mid-pavilion, which took the project past half of all the concrete it needs.
- October 7, 2026. The last piling driven.
- Early 2027. The contractor expects to finish all structural work, then start laying the ipe decking and building the structures on top.
- July 2027. The scheduled reopening.
Two-thirds of the new decking had already arrived by July 24. On land, work on the electrical system, the bathroom and storage renovations, and the foundation is underway. That makes this the season when the pier goes from pilings in the water to a deck someone can picture walking on. The ipe goes down after the concrete is finished, so winter residents will see the frame and summer residents will see the wood.
A different pier comes back
The pier returning in July is the seventh reconstruction of a structure that is now 137 years old, according to Naples Press. Its engineering answers what happened in 2022, when Ian sent about 140 feet of the old pier, including the end shelter and more than 30 pilings, to the floor of the Gulf.
| Previous pier | New pier | |
|---|---|---|
| Piling size | 14 inches square | 18 inches square |
| Piling length | Shorter than the new ones | 70, 85 and 100 feet |
| Deck height | Former elevation | Three feet higher |
| Poured concrete | Former amount | Nearly three times more |
| Food service | Cosmos at the Pier concession, leased from 2015 | Portable carts at the mid-pavilion |
| New additions | None | Underwater camera, Naples Police and Beach Patrol substation |
Turrell, Hall & Associates led the design with MHK Architecture. Naples Press describes MHK as a Naples-based firm. On land, architect Maureen Minker told City Council what changes. The north men's restroom at the pier entry gets a small beach patrol office with its own bathroom, plus a family restroom. A rear changing room becomes pier storage. The women's restroom area on the south side gets a shade structure and benches.
The food is the biggest change. Concessions had been on the pier since 1946, and Cosmos brought the City about $100,000 a year selling pizza, hot dogs, drinks and beach supplies. FEMA ruled that no permanent concession stand could go back above the water. When Council voted unanimously on March 4 to move forward with the design, council member Berne Barton argued for some kind of food service before the vote. Naples Press reported his words:
"We need to try to find a solution that will help appease those who really do want to have some type of food and beverage service out there."
Council looked at a portable cart selling water, ice cream and soda. Council member Linda Penniman said she supported a cart but didn't want anything that would compete with nearby local businesses. In March, plans called for electrical power on the land side to support the cart, and City Manager Gary Young said FEMA would not stop a portable cart from operating on the pier. The City's current project page puts portable food and beverage carts at the mid-pavilion.
Naples Press reported the project's overall cost at $26.3 million. Shoreline Foundation's contract is $23.45 million, which includes a $1.17 million allowance for unforeseen conditions. Funding includes about $12.66 million from the federal government, $11,401,144.20 of it a FEMA grant, along with state grants, $11 million in bonds, $2 million in county tourist development taxes, the City's beach fund, and public donations, including from the Collier Community Foundation.
Part of the old pier is already back in the Gulf
On April 24, 2026, 59 concrete pilings from the old pier, weighing more than 300 tons together, were sunk at Wasmer Reef, 10 miles offshore. That expanded an artificial reef first built in 2015. Shoreline Foundation and Turrell, Hall & Associates handled the reuse under a U.S. Army Corps of Engineers permit, and other demolished concrete went to a facility to be processed into aggregate for future roads, according to the City's April project update. The pier at the end of 12th Avenue South is fenced off this winter, but 59 of its old pilings are already a reef 10 miles out.
If you own a home on the blocks between Broad and 13th, or have been thinking about how the new pier could change those streets once it opens next July, I'd be glad to talk it through over coffee at the market. Reach Mark Paige Riley for a private conversation. Let's Connect.